Question: Use the following data to find the direct labor efficiency variance. Direct labor standard (4.5 hrs.@ $ 6/hr.) $27per finished unit Actual hours worked per

Use the following data to find the direct labor efficiency variance.
Direct labor standard (4.5 hrs.@ $ 6/hr.) $27per finished unit
Actual hours worked per unit 4.0 hrs
Actual units produced 5,400 units
Actual rate per hour $6.25

Group of answer choices

a. $5,400 unfavorable

b. $21,600 unfavorable

c. $21,600 favorable

d. $4,050 favorable

e. 16,200 favorable