Question: Use the following information about a PERT project to answer Q38-39. Times are in days. Assume only one critical path exists which is: B, C,
Use the following information about a PERT project to answer Q38-39.
Times are in days. Assume only one critical path exists which is: B, C, E, F
| Activity | optimistic | Most likely | pessimistic | Critical? | |
| A | 4 | 6 | 9 | No | |
| B | 2 | 3 | 9 | Yes | |
| C | 12 | 14 | 15 | Yes | |
| D | 10 | 28 | 29 | No | |
| E | 3 | 4 | 5 | Yes | |
| F | 2 | 4 | 6 | Yes |
38. What is the expected project completion time?
a. 25.7 days
b. 30.0 days
c. 23.4 days
d. 57.0 days
39. What is the standard deviation of project completion time?
a. 1.47 days
b. 2.17 days
c. 1.06 days
d. 3.44 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
