Question: Paragraph Styles Use the following information about a PERT project to answer Q37-38. Times are in days. Assume only one critical path exists which is:

 Paragraph Styles Use the following information about a PERT project to

Paragraph Styles Use the following information about a PERT project to answer Q37-38. Times are in days. Assume only one critical path exists which is: B, C, E, F Activity | optimistic | Most likely | pessimistic | Critical? A 4 6 9 No B 2 3 9 Yes C 12 14 15 Yes D 10 28 29 No E 3 4 5 Yes F 2 6 Yes 1) What is the expected project completion time? A. 25.7 days B. 30.0 days C. 23.4 days D. 57.0 days