Question: Use the following information for Question #1 and 2. Given the following project information, answer the following questions, assuming the project timeline is 6 months.
Use the following information for Question #1 and 2.
Given the following project information, answer the following questions, assuming the project timeline is 6 months.
PV = $125,000
EV = $100,000
AC = $150,000
BAC = $200,000
For the project:
A) How is the project doing?
B) Is the project ahead or behind schedule?
C) Is the project under or over budget?
D) What is the new estimate at completion (EAC) of the project for the budget?
E) What is the new timeline estimate to complete the project? (How long will the project take to complete based upon your schedule variance and SPI?)
SHOW ALL CALCULATIONS
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock