Question: Use the following information for Question #1 and 2. Given the following project information, answer the following questions, assuming the project timeline is 6 months.

Use the following information for Question #1 and 2.

Given the following project information, answer the following questions, assuming the project timeline is 6 months.

PV = $125,000

EV = $100,000

AC = $150,000

BAC = $200,000

For the project:

A) How is the project doing?

B) Is the project ahead or behind schedule?

C) Is the project under or over budget?

D) What is the new estimate at completion (EAC) of the project for the budget?

E) What is the new timeline estimate to complete the project? (How long will the project take to complete based upon your schedule variance and SPI?)

SHOW ALL CALCULATIONS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!