Question: Use the following information to compress one time unit per move using the least - cost method. The indirect costs for each duration are $

Use the following information to compress one time unit per move using the least-cost method.
The indirect costs for each duration are $500 for 12 days, $400 for 11 days, $300 for 10days, $200 for 9 days, $100 for 8 days.
The Crash Cost per unit time (Slope) is already given and the Maximum crash time is given. Theres no need to calculate.Use the table above to answer the following:
For a time duration of 12 days, what is the total direct, total indirect, and TOTAL project costs.
Please note: you have to give 3 answers (total direct, total indirect, and TOTAL project) to gain the full marks.
Direct Cost: $2000
Indirect Cost: $500
Total Cost: $2500
$400 $600 $2300 $2550 $2600 $450 $2110 $2050 $300

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!