Question: Use the following information to compress one-time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the

Use the following information to compress one-time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost. Note: The correct normal project duration, critical path, and total direct cost are provided. \begin{tabular}{ccccc} \hline & CrashCostAct. & MaximumCrashTime & NormalTime & NormalCost \\ \hline A & 50 & 1 & 3 & 150 \\ B & 100 & 1 & 3 & 100 \\ C & 60 & 2 & 4 & 200 \\ D & 60 & 2 & 3 & 200 \\ E & 70 & 1 & 4 & 200 \\ F & 0 & 0 & 1 & 150 \\ \hline \end{tabular}