Question: Use the following information to develop a schedule The design documents are completed and both the state and local permits have been reviewed, approved and
Use the following information to develop a schedule
- The design documents are completed and both the state and local permits have been reviewed, approved and are ready to pick-up;
- 1 Acre Site Development- approximately 1 of onsite cut/fill;
- Sanitary storm, sanitary sewer, domestic water, natural gas and electrical service are located onsite approx. 100 away from the building pad;
- Parking for 5 trucks and 10 autos is to be provided;
- 5,000 SF single level pre-engineered metal building for warehouse storage (single owner/tenant);
- 1,000 SF of building is to be used (built) for office space;
- The owner/tenant contractually requires that the building is substantially complete ready for use no later than 6 Months from executed contract and notice to proceed.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock