Question: Use the following problem statement to answer questions 2 0 - 2 2 . JKL Company has three jobs to be processed at its bottleneck

Use the following problem statement to answer questions 20-22.
JKL Company has three jobs to be processed at its bottleneck operation. The day when a job arrives, processing time, and promised due dates are given in Table 1. The company wants to determine the job sequence using the EDD rule (see Table 2).[Note: Flow time = finish time + time since job arrived at workstation]Question 20
What is the flow time of job "K"? Round to the nearest whole number.
Question 21
What is the average flow time? Round to four decimal places.
Question 22
What is the average day(s) past due? Round to four decimal places.
Tabio 1
\table[[Iab,\table[[\table[[Tume Since],[Orcter Alvived]]]],\table[[Pracessing],[72ma(days)]],\table[[Qua Dato ldavo],[(rom rraw)]]],[k,12,8,16],[L,11,10,13],[M,17,23,18]]
Toblo 2 eDo rula
\table[[800,\table[[Slant rYme],[idors)]],\table[[Afanessing],[Time]],\table[[Finish nimo],[(doys)]],\table[[Due Dare (derys],[from now)]],\table[[Days],[Pare Due]],\table[[Prene Since],[Order]],\table[[Flonas Virno],[(deys)]]],[,,,,,,,],[,,,,,,,],[,,,,,,,]]
 Use the following problem statement to answer questions 20-22. JKL Company

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!