Question: Use the following problem statement to answer questions 2 3 - 2 5 . A partially completed MPS record for an end item is shown

Use the following problem statement to answer questions 23-25.
A partially completed MPS record for an end item is shown in the table below. The current on-hand inventory (in units), the order quantity (in units), and the lead time (LT, in weeks) are iven in the table. Develop MPS for the end item. Round to the nearest whole number.
Jote: Projected on-hand inventory at the end of this week = On-hand inventory at the end last week + MPS quantity due at start of this week - Projected requirements this week. P for the first week = Projected on-hand inventory at the end of last week + MPS quantity the first week - The cumulative total number of customer orders booked up to (but not uding) the week in which the next MPS quantity arrives.
for the 2 nd,3rd,... weeks = MPS quantity - The cumulative total number of customer ers booked up to (but not including) the week in which the next MPS quantity arrives.]
Question 23
7 pts
Wiat is the available-to "romise imentory (ATP) for weok 3) Round to the noarose whote number.
Question 24
7 Pts
30
15
2
29
3
29
40
Question 25
7 pts
What is the available-to-promise inventory (ATP) for week 1? Round to the nearest whole number.
Current on-hand inventory:
\table[[,1,2,3,4],[Forecast,Order quantity: 45,,,],[Customer orders (booked),17,14,10,8],[Projected on-hand inventory,,13,23,10],[MPS quantity,,,,],[MPS start,,,,],[ATP inventory,,,,]]
 Use the following problem statement to answer questions 23-25. A partially

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!