Question: Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.) Schedule Variance Work Units A B C

Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.)

Schedule Variance Work Units

A

B

C

D

E

F

Total

Planned Value

20

15

10

25

20

20

110

Earned Value

10

10

10

20

25

25

100

Schedule variance

-10

-5

0

-5

5

5

3. Why do so many projects end up terminated as a result of termination through starvation? Discuss the role of ego, power, and politics in this form of project termination.