Question: Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.) Schedule Variance Work Units A B C
Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.)
Schedule Variance Work Units
|
| A | B | C | D | E | F | Total |
| Planned Value | 20 | 15 | 10 | 25 | 20 | 20 | 110 |
| Earned Value | 10 | 10 | 10 | 20 | 25 | 25 | 100 |
| Schedule variance | -10 | -5 | 0 | -5 | 5 | 5 |
|
3. Why do so many projects end up terminated as a result of termination through starvation? Discuss the role of ego, power, and politics in this form of project termination.
Step by Step Solution
There are 3 Steps involved in it