Question: Use the following table to determine the details below: Task Pre Normal Time Crash Time Normal Cost Crash Cost Crash Cost Per Week Crashable Weeks
Use the following table to determine the details below:
| Task | Pre | Normal Time | Crash Time | Normal Cost | Crash Cost | Crash Cost Per Week | Crashable Weeks |
| A | ------- | 4 | 2 | 10,000 | 11,000 |
|
|
| B | A | 3 | 2 | 6,000 | 9,000 |
|
|
| C | A | 2 | 1 | 4,000 | 6,000 |
|
|
| D | B | 5 | 3 | 14,000 | 18,000 |
|
|
| E | B, C | 1 | 1 | 9,000 | 9,000 |
|
|
| F | C | 3 | 2 | 7,000 | 8,000 |
|
|
| G | E, F | 4 | 2 | 13,000 | 25,000 |
|
|
| H | D, E | 4 | 1 | 11,000 | 18,000 |
|
|
| I | H, G | 6 | 5 | 20,000 | 29,000 |
|
|
- Create a Network Diagram showing the ES, EF, LS, LF, and Slack.
- Determine the Project Duration.
- The project is in weeks.
- Determine the Critical Path.
- Determine the Total Normal Cost for the project.
I know the first part, the critical path is A-B-D-H-I IN 22. Can you answer the following in detail? especially the cost to crash by 9 weeks.
- Determine the Crash Cost / Week for each task.
- Determine the number of Crashable weeks for each task.
- Determine the cost to crash the project by nine (9) weeks.
- Determine the New Total Cost of the Project