Question: Use the following table to estimate the time to complete the project. Cost numbers are in thousands of dollar. Duration in weeks Task A
Use the following table to estimate the time to complete the project. Cost numbers are in thousands of dollar. Duration in weeks Task A B C D E LL F G 5 10 15 850 350 400 125 20 1,275650 25 30 35 Plan Complete 1,200 100% 525 100% 1,925 100% 7,650 95% 1,080 75% 125 875 1,000 80% 300 1200 1,500 45% 2800 4,500350 680 400 Monthly Plan 850750 1,4003,4505,1801,1752,07514,880 % Monthly Actual 9006501,3503,8754,780850 2,000