Question: Use the following to answer the next four questions 06 810 A5 G4 E6 C8 F8 have the project indirect cost for each day is

Use the following to answer the next four

Use the following to answer the next four questions 06 810 A5 G4 E6 C8 F8 have the project indirect cost for each day is $1.000. The fol For the network shown above, the project indirect cost for each day is $1,000. The following is the crashing information: Activity Cost per day to crash Number of days activity may be shortened/crashed B $600 1 F $150 1 G $1,400 2. What is the total cost savings af ter crashing the project by one day? $500 @1,250 $1,650 $750 $250