Question: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start Precedes A,B,C D A 38 62 108 E B C

Consider the following work breakdown structure:
Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start Precedes A,B,C D A 38 62 108 E B C 115 End 50 99 100 25 100 65 D IL 90 85 19 91 62 F 31 115 68 E F End End What is the estimated slack time for activity A? 20 days 100 days O days 60 days