Use the given information and the provided table below to determine the least cost AOP
Period Forecast
1 240
2 195
3 385
4 470
5 190
Regular time: $25 per unit (240 units per period maximum)
Overtime: $30 per unit (50 units per period maximum)
Subcontracting: Not available
Temp Workers $35 per unit (40 units per month maximum)
Beginning Inv.: 75
Holding cost: $3 per unit per period
Backorder cost: $5 per unit per period