Question: Use the information below to answer the question The precedence diagram of a project is provided as follows. All task dependencies are Finish - to

Use the information below to answer the question
The precedence diagram of a project is provided as follows. All task dependencies are Finish-to-Start and the time unit is in days.
What is the duration of this project?
27 days
25 days
21 days
18 days
 Use the information below to answer the question The precedence diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!