Question: Use the information below to construct a project network using the activity - on - node ( AON ) method in order to answer questions

Use the information below to construct a project network using the activity-on-node (AON) method in order to answer questions that follow.
Activity A (Predecessor: none),(Duration in days: 3)
Activity B -(Predecessor: A),(Duration in days: 1)
Activity C -(Predecessor: A),(Duration in days: 4)
Activity D -(Predecessor: B),(Duration in days: 1)
Activity E -(Predecessor: B, C),(Duration in days: 2)
Activity F -(Predecessor: E),(Duration in days: 8)
Activity F -(Predecessor: D),(Duration in days: 2)
Activity G -(Predecessor: E),(Duration in days: 3)
Activity H -(Predecessor: E),(Duration in days: 3)
Activity I -(Predecessor: F, G, H),(Duration in days: 1)
Activity J -(Predecessor: I),(Duration in days: 1)
What is the late finish (LF) time for activity E? a.9 b.13 c.15 d.14 e.7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!

Q: