Question: Use the information below to construct a project network using the activity-on- node (AON) method in order to answer questions that follow. Activity ID A

Use the information below to construct a project network using the activity-on- node (AON) method in order to answer questions that follow. Activity ID A B C D E F G I || |J Predecessor None A A B B, C E D E F, G, H I Dur 3 1 4 1 2 8 2 3 11 1

What is the earliest start (ES) time for activity I?

a.

7

b.

17

c.

12

d.

15

e.

9