Question: Use the information below to estimate the completion time for a project. a. Assume a conversion rate of 13 function points each person-month. b. Assume


Use the information below to estimate the completion time for a project. a. Assume a conversion rate of 13 function points each person-month. b. Assume the project has a high complexity level (score = 1.35). Team: 8 members Components: Complexity Factors: 20.65 months 15.18 months 13.38 months 9.49 months