Question: Use the information contained below to compress one time unit per move using the Main Content ethod. Answer questions 64 through 67. Activity A
Use the information contained below to compress one time unit per move using the Main Content ethod. Answer questions 64 through 67. Activity A B C D E F Predecessor None A A B D, E Duration 1 wk 3 wks 4 wks 3 wks 4 wks 3 wks Normal Cost $100 $150 $200 $200 $200 $150 Max. Amount Activity Can be Reduced 0 2 wks 1 wk 1 wk 2 wks 1 wk Cost to Reduce Max. Amount 0 $200 $50 $60 $140 $90 Crash Slope If you want to reduce the project the maximum amount it can be reduced, what will be the total project direct cost?
Step by Step Solution
There are 3 Steps involved in it
In order to calculate the total direct cost of the project if it is reduced by the maximum amount po... View full answer
Get step-by-step solutions from verified subject matter experts
