Question: Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point
| Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost. Note crash time refers to the amount of time it will take to complete the activity after crashing. | ||||||
| Activity ID | Predecessor(s) Activity | Normal time | Normal cost | Crash Time | Crash Cost | |
| A | None | 5 | 50 | 4 | 80 | |
| B | None | 3 | 60 | 1 | 180 | |
| C | A | 4 | 70 | 4 | 70 | |
| D | A | 2 | 50 | 1 | 60 | |
| E | B | 5 | 100 | 2 | 280 | |
| F | C | 2 | 90 | 1 | 190 | |
| G | D | 5 | 50 | 4 | 80 | |
| H | E | 2 | 60 | 2 | 60 | |
| I | F, G, H | 3 | 200 | 2 | 400 | |
| Total direct normal costs | $730 | |||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock