Question: EX 9 - 2 ( Static ) Use the information contained below... Use the information contained below to compress one - time unit per move

EX9-2(Static) Use the information contained below...
Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost.
Activity Crash cost Maximum
ID (Slope) Crash Time Normal time Normal cost
A 02150
B 10013100
C 5026200
D 4014200
E 5513200
F 01150
Total direct normal costs $1,000
To compress from time period 13 to time 12 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
check all that apply 1
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
To compress from time period 12 to time 11 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
check all that apply 2
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
To compress from time period 11 to time 10 crash the following activity(s)(You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)
What is the adjusted total cost of period 12?
What is the adjusted total cost at time period 11?
What is the adjusted cost at time period 10?
check all that apply 3
Aunanswered
Bunanswered
Cunanswered
Dunanswered
Eunanswered
Funanswered
What is the crash point of the network?
Time period_____weeks?
Total cost $____?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!