Question: Use the information contained below to compress one-time unit per move using the least cost method . Reduce the schedule until you reach the crash

Use the information contained below to compress one-time unit per move using the least cost method.

Reduce the schedule until you reach the crash point of the network.

For each move identify what activity(ies) was crashed and the adjusted total cost.

Activity ID Crash Cost Slope Max crash time Normal Time Normal Cost Crash Time Crash Cost
A $0 0 3 $150 3 $150
B $50 2 4 $100 2 $200
C $30 2 7 $200 5 $260
D $40 2 3 $200 1 $280
E $50 1 2 $200 1 $250
F $60 1 6 $150 5 $210

Use the information contained below to compress

What is the total direct cost of the project?

Reduce the schedule until you reach the maximum crash point (crash duration) of the network.

What is the project duration at the crash point? What is the total direct cost for the project at the crashing point?

If the indirect costs for each project duration are:

$300 (20 time units), $220 (19), $140 (18), $80 (17), and $60 (16), $40 (15),

compute the total project cost for each duration. Fill in the table below.

Time unit

Total direct

cost

Total indirect cost Total cost

What is the optimum cost-time schedule for the project? Indicate the time unit.

What is this cost to crash the project to the optimum cost-time schedule?

7 Ax B F 3 4 6 D E 3 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!