Question: Use the information in the table to compute the expected completion time for the project where activity lengths are given in days. Activity Expected time
Use the information in the table to compute the expected completion time for the project where activity lengths are given in days.
| Activity | Expected time | Predecessor |
| A | 6 | -- |
| B | 3 | A |
| C | 7 | A |
| D | 5 | B |
| E | 10 | C |
| F | 8 | D, E |
| G | 6 | E,F |
| H | 4 | F, G |
| J | 10 | G |
| K | 5 | H, J |
| 41 days | ||
| 52 days | ||
| 47 days | ||
| 65 days | ||
| 70 days |