Question: Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 5 B -- 8 C -- 3 D

Use the following data for problems 34, 35, and 36

Activity Activity Predecessor Time (days)
A -- 5
B -- 8
C -- 3
D A, B, C 12
E A, B, C 7
F D, E 9
G D, E 15
H D, E 4
I G 4
J H 3
K I, J 6

  1. The expected completion time for the project above is?
    1. 34 days
    2. 52 days
    3. 76 days
    4. 45 days

  1. The critical path for the project above is?
    1. A, E, G, I, K
    2. B, E, J, K
    3. B, D, G, I, K
    4. A, B, E, G, I, K

  1. How much slack is there in activity F?
    1. 16 days
    2. 1 days
    3. 8 days
    4. 0 days (no slack)