Question: Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 5 B -- 8 C -- 3 D
Use the following data for problems 34, 35, and 36
| Activity | Activity Predecessor | Time (days) |
| A | -- | 5 |
| B | -- | 8 |
| C | -- | 3 |
| D | A, B, C | 12 |
| E | A, B, C | 7 |
| F | D, E | 9 |
| G | D, E | 15 |
| H | D, E | 4 |
| I | G | 4 |
| J | H | 3 |
| K | I, J | 6 |
- The expected completion time for the project above is?
- 34 days
- 52 days
- 76 days
- 45 days
- The critical path for the project above is?
- A, E, G, I, K
- B, E, J, K
- B, D, G, I, K
- A, B, E, G, I, K
- How much slack is there in activity F?
- 16 days
- 1 days
- 8 days
- 0 days (no slack)