Question: Use the network diagram and the table to answer the following questions: table [ [ ACTIVITY , OPTIMISTIC, table [ [ MOST ]

Use the network diagram and the table to answer the following questions:
\table[[ACTIVITY,OPTIMISTIC,\table[[MOST],[LIKELY]],PESSIMISTIC,\table[[EXPECTED],[TIME]],VARIANCE],[A,N/A,N/A,N/A,2,0.2],[B,N/A,N/A,N/A,3,0.8],[C,N/A,N/A,N/A,5,0.7],[D,N/A,N/A,N/A,4,1.2],[E,N/A,N/A,N/A,2,0.6],[F,3,4.5,9,,],[G,N/A,N/A,N/A,4,1],[H,1,2,3,,],[I,NA,N/A,N/A,14,2]]
a. What are the expected durations and variances of activities F and H?
b. What are the critical activities?
c. What is the expected project completion time?
d. What is the variance of project completion time?
e. What is the probability that this project can be complete in fewer than 25 days?
 Use the network diagram and the table to answer the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!