Question: 14. Use the network diagram and the table to answer the following questions A PE B Start Finish E 11 JH ACTIVITY OPTIMISTIC MOST UKELY

14. Use the network diagram and the table to
14. Use the network diagram and the table to answer the following questions A PE B Start Finish E 11 JH ACTIVITY OPTIMISTIC MOST UKELY PESSIMISTIC EXPECTED TIME VARIANCE NA N/A N/A 2 0.2 B N/A N/A N/A 3 0.8 N/A N/A N/A 5 017 D N/A N/A N/A 4 1.2 E N/A N/A N/A 2 0.6 F 3 45 9 G NA N/A 4 H 1 2 3 I NA N/A N/A 14 2 a. What are the expected durations and variances of activities Fand H? b. What are the critical activities? What is the expected project completion time? d. What is the variance of project completion tims