Question: Use the network diagram provided below to answer the following question: ES EF E LS LF 20 start wa end 10 : G Which activity

Use the network diagram provided below to answer

Use the network diagram provided below to answer the following question: ES EF E LS LF 20 start wa end 10 : G Which activity has the most slack? O a) Activity D Ob) Activity F c) Activity E d) Activity A e) Activity B