Question: Question 31 (1 point) Use the network diagram provided below to answer the following question: ES EF LS LF 20 start end B 10 What

Question 31 (1 point) Use the network diagramQuestion 31 (1 point) Use the network diagram

Question 31 (1 point) Use the network diagram provided below to answer the following question: ES EF LS LF 20 start end B 10 What is activity B's latest start time? a) Week 14 Ob) Week 10 c) Week 18 d) Week 5 e) Week o Question 32 (1 point) Use the network diagram provided below to answer the following question: ES LS LF 20 start end 19 B 10 If activity E is delayed by 3 weeks (and all other activities occur at their normal duration), the project duration will a) increase by 1 week b) not change c) increase by 4 weeks d) increase by 3 weeks e) increase by 2 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!