Question: Use the nodal method to develop your project network. Show your network with the activity early, late, and slack times. Indicate below the critical path:
Use the nodal method to develop your project network. Show your network with the activity early, late, and slack times. Indicate below the critical path:
ID Description Predecessor Duration
A Do Survey None
B Write Soils Report A
C Do Traffic Design A
D Design Lot Layout A
E Approve design B C D
F Design Illumination C
G Drainage D
H Landscape G
I Signing H
J Bid Proposal F G H I