Question: Use the nodal method to develop your project network. Show your network with the activity early, late, and slack times. Indicate below the critical path:

Use the nodal method to develop your project network. Show your network with the activity early, late, and slack times. Indicate below the critical path:
ID Description Predecessor Duration
A Do Survey None 5
B Write Soils Report A 10
C Do Traffic Design A 20
D Design Lot Layout A 15
E Approve design B, C, D 60
F Design Illumination C 15
G Drainage D 40
H Landscape G 20
I Signing H 10
J Bid Proposal F, G, H, I 10