Question: Use the precedence diagram provided for this lab to answer this question. If workstation # 1 is ( I , B ) ( 5 9
Use the precedence diagram provided for this lab to answer this question. If workstation # is IB seconds then which of the following would NOT be an acceptable workstation #
EFD
ADJ
EF
DC
AC
ADE