Question: Question # 1 4 Use the precedence diagram provided for this lab to answer this question. If workstation # 1 is ( I , D
Question #
Use the precedence diagram provided for this lab to answer this question. If workstation # is I D seconds and workstation # is AC seconds then which of the following would NOT be an acceptable workstation #
a BEF
b
c BJE
d BJK
e
f
Question #
Use the precedence diagram provided for this lab to answer this question. If workstation # is IB seconds then which of the following would NOT be an acceptable workstation #
a
b ADE
c
d ADJ
e
f EFD