Question: Use the project, answer questions Time Estimates Activity a m b Immediate predecessors - - - - - - - - - - - -

Use the project, answer questions
Time Estimates
Activity a m b Immediate predecessors
----------------------------------------------------
A 61014--
B 8913 A
C 41220 A
D 6810 B, C