Question: Use the project, answer questions Time Estimates Activity a m b Immediate predecessors A , 6 , 1 0 , 1 4 8 , 9

Use the project, answer questions
Time Estimates
Activity a m b Immediate predecessors
A
,
6
,
10
,
14
8
,
9
,
13
C 4
,
12
,
20
,
A
D
,
6
,
8
,
10
B
,
C
What is the critical path?