Question: Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four

  1. Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project.

    Activity Duration Predecessor
    A 5 days --
    B 4 days A
    C 5 days A
    D 8 days B
    E 6 days C, D
    F 6 days E

    32 hours

    40 hours

    48 hours

    6 hours