Question: Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four
-
Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project.
Activity Duration Predecessor A 5 days -- B 4 days A C 5 days A D 8 days B E 6 days C, D F 6 days E 32 hours
40 hours
48 hours
6 hours