Question: Use the project network diagram below to determine the project schedule (ES, EF, LS, LF). 'Take your time and draw this on paper and carefully

Use the project network diagram below to determine the project schedule (ES, EF, LS, LF). 'Take your time and draw this on paper and carefully go through it, one mistake can affect many of the other values. Consider a project with the following activity paths for the network: A.b-f-G (2. days) A.C-Du (28 days) A.HJJ (24 days) if activity D is shertened by 5 days, by how many days will the duration of the croiect be shortened? Answer: Consider a project with the following activity paths for the network: A.B.E.G (40 days) A.C-D-J (38 days) A.H-J (36 days) if the duration of activity J is increased by 7 days. by how many days will the duration of the proiect be increased