Question: Use the provided project task information to create a schedule for the below project by hand, then answer the following questions. a . List the

Use the provided project task information to create a schedule for the below project by hand,
then answer the following questions.
a. List the activities are on the project's critical path:
b. Calculate the shortest overall duration for the project:
c. Discern which activity has the longest float:
d. Calculate the float for the activity referenced in part c: