Question: Use the scenario below to answer questions 2 - 7 Activity Predecessors A Duration (weeks) 5 B 6 C A 4 D A 3 E

Use the scenario below to answer questions 2 - 7
Use the scenario below to answer questions 2 - 7
Use the scenario below to answer questions 2 - 7
Use the scenario below to answer questions 2 - 7 Activity Predecessors A Duration (weeks) 5 B 6 C A 4 D A 3 E A 1 F E 4 G 14 H DF , GH 12 1 2 5. What is the project's expected completion date? A. 20 weeks B. 23 weeks C. 24 weeks D. 26 weeks 6. What activities are considered to be non-critical activities? A B,C,D,H B. A,C,H,I C. B,H,1 D. A,E,F,G,I 7. Which activities have their latest finish time equal to their earliest finish time? A. B, H, B. A,C,H, C. A,E,F,G,1 D. B,C,D, 8. The earliest string time for an activity leaving a node: A. is the max.um of the earliest finish time for all activities leaving the node B. is equal to the earliest finish time for the same activity minus its expected activity time C. depends on all paths leading from the starting to the finishing node D. depends on the earliest finish and the latest start

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!