Question: (2 points total, 70% content, 30% communication quality). Using the data in the table below: a. Create the precedence diagram for the project b. Determine

(2 points total, 70% content, 30% communication quality). Using the data in the table below: a. Create the precedence diagram for the project b. Determine the minimum cost schedules for: i. a 21-week completion time ii. a 19-week completion time c. Determine the minimum duration for the project. Report the associated cost.

Activity Predecessors

Normal Duration

(Weeks)

Crash Duration

(Weeks)

Normal Cost

($Thousands)

Crash Cost

($Thousands)

A - 6 4 100 160
B - 10 7 40 130

C

A 8 6 30 120
D A,B 7 4 50 155
E B 5 4 70 85
F C 4 2 60 140
G D,E,F 8 4 50 250

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!