Question: (2 points total, 70% content, 30% communication quality). Using the data in the table below: a. Create the precedence diagram for the project b. Determine
(2 points total, 70% content, 30% communication quality). Using the data in the table below: a. Create the precedence diagram for the project b. Determine the minimum cost schedules for: i. a 21-week completion time ii. a 19-week completion time c. Determine the minimum duration for the project. Report the associated cost.
| Activity | Predecessors | Normal Duration (Weeks) | Crash Duration (Weeks) | Normal Cost ($Thousands) | Crash Cost ($Thousands) |
| A | - | 6 | 4 | 100 | 160 |
| B | - | 10 | 7 | 40 | 130 |
| C | A | 8 | 6 | 30 | 120 |
| D | A,B | 7 | 4 | 50 | 155 |
| E | B | 5 | 4 | 70 | 85 |
| F | C | 4 | 2 | 60 | 140 |
| G | D,E,F | 8 | 4 | 50 | 250 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
