Question: Use the spreadsheet below to finish this assignment. You need to interpret the project progress based on the information. For this exercise, you only need

Use the spreadsheet below to finish this assignment. You need to interpret the project progress based on the information. For this exercise, you only need to look at the datasets and see how each project performs in terms of schedule and cost control. Calculating the BAC and EAC is not required. When you answer the question, please make sure that you evaluate each project separately. Thank you!

Use the spreadsheet below to finish this

Use the spreadsheet below to finish this

Use the spreadsheet below to finish this

Use the spreadsheet below to finish this

Data Set 1 \begin{tabular}{|r|r|r|r|r|r|} \hline \multicolumn{1}{|l|}{ Week } & \multicolumn{1}{l|}{ EV } & \multicolumn{1}{l|}{ PV } & \multicolumn{1}{l|}{ AC } & \multicolumn{1}{l|}{ SPI } & \multicolumn{1}{l|}{ CPI } \\ \hline 1 & 5 & 6 & 6 & 0.83 & 0.83 \\ \hline 2 & 15 & 20 & 20 & 0.75 & 0.75 \\ \hline 3 & 20 & 25 & 25 & 0.80 & 0.80 \\ \hline 4 & 45 & 45 & 45 & 1.00 & 1.00 \\ \hline 5 & 55 & 52 & 50 & 1.06 & 1.10 \\ \hline 6 & 65 & 57 & 55 & 1.14 & 1.18 \\ \hline 7 & 80 & 70 & 60 & 1.14 & 1.33 \\ \hline 8 & 90 & 80 & 67 & 1.13 & 1.34 \\ \hline 9 & 100 & 95 & 100 & 1.05 & 1.00 \\ \hline 10 & 102 & 105 & 118 & 0.97 & 0.86 \\ \hline 11 & 120 & 130 & 130 & 0.92 & 0.92 \\ \hline 12 & 140 & 150 & 145 & 0.93 & 0.97 \\ \hline 13 & 170 & 175 & 155 & 0.97 & 1.10 \\ \hline 14 & 195 & 200 & 225 & 0.98 & 0.87 \\ \hline 15 & 220 & 225 & 250 & 0.98 & 0.88 \\ \hline 16 & 245 & 255 & 265 & 0.96 & 0.92 \\ \hline 17 & 280 & 300 & 325 & 0.93 & 0.86 \\ \hline 18 & 325 & 350 & 380 & 0.93 & 0.86 \\ \hline 19 & 380 & 440 & 460 & 0.86 & 0.83 \\ \hline 20 & 440 & 525 & 550 & 0.84 & 0.80 \\ \hline \end{tabular} Data Set 2 \begin{tabular}{r|r|r|r|r|r|} \multicolumn{1}{l}{ Week } & \multicolumn{1}{l|}{ EV } & \multicolumn{1}{l}{ PV } & \multicolumn{1}{l|}{ AC } & \multicolumn{1}{l|}{ SPI } & \multicolumn{1}{l}{ CPI } \\ \hline 1 & 5 & 5 & 6 & 1.00 & 0.83 \\ \hline 2 & 15 & 15 & 20 & 1.00 & 0.75 \\ \hline 3 & 20 & 21 & 25 & 0.95 & 0.80 \\ \hline 4 & 45 & 45 & 55 & 1.00 & 0.82 \\ \hline 5 & 55 & 52 & 68 & 1.06 & 0.81 \\ \hline 6 & 65 & 57 & 73 & 1.14 & 0.89 \\ \hline 7 & 80 & 70 & 90 & 1.14 & 0.89 \\ \hline 8 & 90 & 80 & 95 & 1.13 & 0.95 \\ \hline 9 & 100 & 95 & 100 & 1.05 & 1.00 \\ \hline 10 & 102 & 105 & 118 & 0.97 & 0.86 \\ \hline 11 & 120 & 130 & 135 & 0.92 & 0.89 \\ \hline 12 & 140 & 150 & 160 & 0.93 & 0.88 \\ \hline 13 & 170 & 175 & 190 & 0.97 & 0.89 \\ \hline 14 & 195 & 200 & 235 & 0.98 & 0.83 \\ \hline 15 & 220 & 225 & 255 & 0.98 & 0.86 \\ \hline 16 & 245 & 255 & 275 & 0.96 & 0.89 \\ \hline 17 & 280 & 300 & 325 & 0.93 & 0.86 \\ \hline 18 & 325 & 350 & 380 & 0.93 & 0.86 \\ \hline 19 & 380 & 385 & 460 & 0.99 & 0.83 \\ \hline 20 & 440 & 445 & 550 & 0.99 & 0.80 \\ \hline \end{tabular} Data Set 3 \begin{tabular}{|r|r|r|r|r|r|} \hline \multicolumn{1}{|l|}{ Week } & \multicolumn{1}{l|}{ EV } & \multicolumn{1}{l|}{ PV } & \multicolumn{1}{l|}{ AC } & \multicolumn{1}{l|}{ SPI } & \multicolumn{1}{l|}{ CPI } \\ \hline 1 & 5 & 5 & 4 & 1.00 & 1.25 \\ \hline 2 & 15 & 15 & 12 & 1.00 & 1.25 \\ \hline 3 & 20 & 21 & 21 & 0.95 & 0.95 \\ \hline 4 & 45 & 45 & 49 & 1.00 & 0.92 \\ \hline 5 & 55 & 52 & 53 & 1.06 & 1.04 \\ \hline 6 & 65 & 57 & 65 & 1.14 & 1.00 \\ \hline 7 & 80 & 70 & 85 & 1.14 & 0.94 \\ \hline 8 & 90 & 80 & 95 & 1.13 & 0.95 \\ \hline 9 & 100 & 95 & 100 & 1.05 & 1.00 \\ \hline 10 & 102 & 105 & 105 & 0.97 & 0.97 \\ \hline 11 & 120 & 130 & 120 & 0.92 & 1.00 \\ \hline 12 & 140 & 150 & 130 & 0.93 & 1.08 \\ \hline 13 & 170 & 175 & 150 & 0.97 & 1.13 \\ \hline 14 & 195 & 200 & 175 & 0.98 & 1.11 \\ \hline 15 & 220 & 225 & 215 & 0.98 & 1.02 \\ \hline 16 & 245 & 255 & 248 & 0.96 & 0.99 \\ \hline 17 & 280 & 300 & 290 & 0.93 & 0.97 \\ \hline 18 & 325 & 350 & 350 & 0.93 & 0.93 \\ \hline 19 & 380 & 385 & 380 & 0.99 & 1.00 \\ \hline 20 & 440 & 445 & 450 & 0.99 & 0.98 \\ \hline \end{tabular} Data Set 4 \begin{tabular}{|r|r|r|r|r|r|} \hline \multicolumn{1}{|l|}{ Week } & \multicolumn{1}{l|}{ EV } & \multicolumn{1}{l|}{ PV } & \multicolumn{1}{l|}{ AC } & \multicolumn{1}{l|}{ SPI } & \multicolumn{1}{l|}{ CPI } \\ \hline 1 & 5 & 4 & 4 & 1.25 & 1.25 \\ \hline 2 & 15 & 12 & 12 & 1.25 & 1.25 \\ \hline 3 & 20 & 20 & 21 & 1.00 & 0.95 \\ \hline 4 & 45 & 45 & 49 & 1.00 & 0.92 \\ \hline 5 & 55 & 52 & 53 & 1.06 & 1.04 \\ \hline 6 & 65 & 57 & 67 & 1.14 & 0.97 \\ \hline 7 & 80 & 70 & 85 & 1.14 & 0.94 \\ \hline 8 & 90 & 80 & 95 & 1.13 & 0.95 \\ \hline 9 & 100 & 95 & 100 & 1.05 & 1.00 \\ \hline 10 & 102 & 105 & 105 & 0.97 & 0.97 \\ \hline 11 & 120 & 130 & 120 & 0.92 & 1.00 \\ \hline 12 & 140 & 150 & 130 & 0.93 & 1.08 \\ \hline 13 & 170 & 190 & 150 & 0.89 & 1.13 \\ \hline 14 & 195 & 215 & 175 & 0.91 & 1.11 \\ \hline 15 & 220 & 250 & 215 & 0.88 & 1.02 \\ \hline 16 & 245 & 280 & 248 & 0.88 & 0.99 \\ \hline 17 & 280 & 330 & 290 & 0.85 & 0.97 \\ \hline 18 & 325 & 380 & 350 & 0.86 & 0.93 \\ \hline 19 & 380 & 445 & 380 & 0.85 & 1.00 \\ \hline 20 & 440 & 530 & 450 & 0.83 & 0.98 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!