Question: Use the table below to answer the following questions: Activity Preceding Activity Estimate in Months A None 2 B A 4 C A 2 D
Use the table below to answer the following questions:
| Activity | Preceding Activity | Estimate in Months |
| A | None | 2 |
| B | A | 4 |
| C | A | 2 |
| D | B | 2 |
| E | B, C | 6 |
| F | A | 6 |
| H | D, E, F | 2 |
Question 1: Draw the network diagram using the information provided in the table above. (5 points)
Question 2: Which path is the critical path and what is the duration of the critical path? (1 point)
Question 3: When is the earliest time that activity D can be completed? Explain your answer. (2 point)
Question 4: When is the latest time that activity F must be completed in order that the project is not delayed? Explain your answer. (2 point)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock