Question: Use the table below to answer the following questions: Question 1: Draw the network diagram using the information provided in the table above. ( 3

 Use the table below to answer the following questions: Question 1:

Use the table below to answer the following questions: Question 1: Draw the network diagram using the information provided in the table above. ( 3 points) Question 2: What is the duration of the critical path? Explain your answer. (1 point) Question 3: What is the float of activity B? Explain your answer. (1 point) Question 4: What is the float of activity E? Explain your answer. (1 point) Question 5: What is the float of activity D? Explain your answer. ( 1 point) Question 6: The project manager is planning to shorten the project schedule. The PM has asked to remove the work of activity E from the project, making activity D the predecessor to activities G and E. Draw the new network diagram. What will be the effect on the critical path? (3 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!