Question: Use the table of information below to (a.) create a critical path diagram, (b.) calculate the critical path duration, and (c.) attempt to crash to

Use the table of information below to (a.) create
Use the table of information below to (a.) create a critical path diagram, (b.) calculate the critical path duration, and (c.) attempt to crash to schedule for the least amount of cost to 21 days. Task Predecessor(s) Duration Days 'Crashable Cost to crash (per day) A 5 0 NA B A 6 1 $800 A 4 0 NA D 1 $450 BC D E 8 2 $400 $100 F D 9 2