Question: Use this Activity-on-Node (AON) diagram to determine the Early Start, Latest Start, Earliest Finish, Latest Finish, Slack, Critical Path and Project Duration. You will only
Use this Activity-on-Node (AON) diagram to determine the Early Start, Latest Start, Earliest Finish, Latest Finish, Slack, Critical Path and Project Duration. You will only enter only certain answers online but you will need to calculate all to get the required answers.

Earliest start time for Node 5
Latest start time for Node 5
Earliest finish time for Node 5
Latest finish time for Node 5
Slack time for Node 5
Earliest start time for Node 7
Latest start time for Node 7
Earliest finish time for Node 7
Latest finish time for Node 7
Slack time for Node 7
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts