Question: Use this info for questions 1 4 - 1 9 . Determine the lowest cost plan for crashing this project by six periods. What is

Use this info for questions 14-19.
Determine the lowest cost plan for crashing this project by six periods.
What is the expected project duration before crashing any activities?
\table[[Activity,Normal Time,Possible Crashes,Crash Cost Per Day],[A,3,1,224],[B,12,3,84],[C,11,1,125],[D,13,2,117],[E,12,3,99],[F,7,1,80]] Find all the critical paths. Cost of the second crash? Cost of the fourth crash? Cost of the fifth crash? Total cost of crashing the project?
 Use this info for questions 14-19. Determine the lowest cost plan