Question: Use this network diagram for question. What is the expected duration of the project? (enter a whole number) What is the critical path for this

Use this network diagram for question.

Use this network diagram for question. What is

What is the expected duration of the project? (enter a whole number)

What is the critical path for this project? What is the early finish time for activity F? What is the early start time for activity E? What is the late finish time for activity A? What is the late start time for activity E? What is the slack time for activity C?

C,22 D,1 F,4 A, 18 G,15 B,24 E,3