Question: Using a waste factor of 7 % , determine the number f cubic yards of concrete needed to pour the continuous footing and shown in

Using a waste factor of 7%, determine the number f cubic yards of concrete needed to pour the continuous footing and shown in Figure 1 and 2 below. Assume that the wall is centered over the footing
Figure 1: Foundation Plan
Figure L: roundation section
Determine the amount of rebar needed for the continuous footing shown in figure 1 and 2. Allow 2 inches of cover and extend the dowels 15 inches into the wall. Add 10% for lap and waste to the continuous bars.
Determine the number of linear feet of form needed for the continuous footing shown in figure 1 and 2.
Using a waste factor of 8 percent, determine the number f cubic yards of concrete needed to pour two of the spread footings in Figure 3
Determine the amount of rebar needed for two of the spread footings shown in figure 3. Allow for 2 inches of cover.
Using a waste factor of 7 % , determine the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!