Question: Using Activity on Arrow ( AOA ) , draw the network for a small construction project consisting of the following activity and prepare all CPM

Using Activity on Arrow (AOA), draw the network for a small construction project consisting of the following activity and prepare all CPM calculations that include the ES, EF, LS, LF, TF, FF and IF and indicate the Critical path.
Activity G (3 weeks) and Activity H (5 Weeks) both follow F (2 weeks) and C (5 weeks)
Activity D (7 weeks) follows both B (3 weeks) and C (5 weeks).
Activity J (8 weeks) follows E (5 weeks) and precedes L (2 weeks)
Activity C precedes both F and D
Activity L follows both J and K (3 weeks)
Activity K follows D and precedes L
Activity M (4 weeks) follows G
Activity A (5 weeks) commences the project
Activity N (2 weeks) follows H
Activities B and C follow A
Activity E follows A & B and precedes J
Activity F follows C and precedes G and H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!