Question: Using Activity on Arrow ( AOA ) , draw the network for a small construction project consisting of the following activity and prepare all CPM
Using Activity on Arrow AOA draw the network for a small construction project consisting of the following activity and prepare all CPM calculations that include the ES EF LS LF TF FF and IF and indicate the Critical path.
Activity G weeks and Activity H Weeks both follow F weeks and C weeks
Activity D weeks follows both B weeks and C weeks
Activity J weeks follows E weeks and precedes L weeks
Activity C precedes both F and D
Activity L follows both J and K weeks
Activity K follows D and precedes L
Activity M weeks follows G
Activity A weeks commences the project
Activity N weeks follows H
Activities B and C follow A
Activity E follows A & B and precedes J
Activity F follows C and precedes G and H
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock