Question: Using all paths through the project network, estimate the probability that the project will be completed within 30 days. Compare your answer to the answer

Using all paths through the project network, estimate the probability that the project will be completed within 30 days. Compare your answer to the answer in part e and explain. Round your answers for values to 2 decimal places and for probability values to 4 decimal places. For path B-D-F: fill in the blank 64 0.0643 Cumulative probability fill in the blank 65 1 For path A-F: fill in the blank 66 Cumulative probability fill in the blank 67 1 fill in the blank 68